Recent content by Henny and Bea

  1. The Beginnings

    The Beginnings

    The beginnings. Beds block base to raise off the ground. Old fly-wire door ready to re-purpose. First pallet down.
  2. Initial Structure

    Initial Structure

    Initial structure coming along.
  3. First site inspection

    First site inspection

    First site inspection in progress.
  4. Taking shape

    Taking shape

    Taking shape. Using up old house paint.
  5. Surprise donated roof- lucky fit!

    Surprise donated roof- lucky fit!

    A donated roof structure halfway through the project.It just fit and saved a lot of work. I had initially planned a sloped roof so the pitched roof meant I had to redesign everything.
  6. Roofing nearly done

    Roofing nearly done

    Roofing on and designed to let the hot air out through the peak.
  7. Roof on, nearly there

    Roof on, nearly there

    Nearly there.
  8. Inside - stairs to laying boxes and perches

    Inside - stairs to laying boxes and perches

    Donated floor-board appearance linoleum.Removable stairs for cleaning. Laying tubs in background also removable for easy cleaning.
  9. Human entrance

    Human entrance

    Human entrance through cut down wire door.Have to bend down to enter but can stand up inside.
  10. Storage access

    Storage access

    Storage built in under laying area and easily accessible from outside. Access to laying boxes via separate door above.
  11. Another site inspection

    Another site inspection

    Site inspection in progress.Stairs have passed!
  12. Perch inspection

    Perch inspection

    Site inspection- roosts seem good!
  13. Ready!

    Ready!

    Chicken Hilton.Front entrance unhooks to be front door.
  14. Aussie Chicken Hilton

    Aussie Chicken Hilton

    Aussie Chicken Hilton
  15. Detailed perch inspection- passed!

    Detailed perch inspection- passed!

    Site inspection- Roosting perches are removable for cleaning. Have since added poop tray beneath for easy cleaning.