@Blooie tomorrow is his B-Day and it is only 6 hours from now (here). You can't throw him out NOW! OK, dish, what did he do???
Cap, you need to take over from the incapable men folk. Barring that I would hire an electrician to check the work when they are done, I fear a fire is in your future. It doesn't take 2 days to hook up a building, it is done AFTER you:
- Put the fixture boxes in the goat shed
- Run wires from the panel where the power will come into the building to the fixtures
- Put the fixtures in
- Run conduit underground from the box at the house to the box on the goat shed
- Run wire through the conduit
- Run wire from the box at the house to the service panel
THEN they shut the power off while they connect the 3 wires into the panel (after shutting off power to the panel of course) which takes but a few minutes and your workshop isn't without power very long.