Coop building has started! Yeah! It will be a coop/run combo. 12'x6' with the coop portion being 1/3 of the structure at 4'x6'. Front wall is 7' tall and back is 6'. It looks super tall because of the extra 18" of block in the front. The hens will have a view of Mt. Shasta.
First hole being dug.
Day 1 (Feb 3, 2013): Dug eight holes. Put in sonotubes. Mixed and poured concrete into tubes. Set metal post brackets in wet concrete. Covered them up with multiple layers of cardboard/blankets/etc and a tarp over it all to prevent the concrete from freezing before it had time to set.
Day 2 (Feb 9, 2013): Dug down about 6-8" between concrete. Leveled the bottom of the trench with sand and set concrete blocks all around to get a level perimeter. Front is about 18" higher than the back over 6' distance.
End of second day.
Day 3 (Feb 10, 2013): Framed up main structure in garage. Predrilled and precut everything. Moved the front and back walls separately and then started attaching the rafters. Attached plywood and tar paper. Then mocked up the tin roof. It isn't attached yet. Just held on with clamps for the moment. Since it is used roofing that was a find, it needs to come down to have my husband do his metal magic to fix the holes.
Mock up in the garage.
Plywood going on roof.
End of third day.
I am thinking at the rate we're going that we might actually be done by the time the eggs get here on the 20th. If not, then soon after.
What do you guys think?
Rachel
First hole being dug.
Day 1 (Feb 3, 2013): Dug eight holes. Put in sonotubes. Mixed and poured concrete into tubes. Set metal post brackets in wet concrete. Covered them up with multiple layers of cardboard/blankets/etc and a tarp over it all to prevent the concrete from freezing before it had time to set.
Day 2 (Feb 9, 2013): Dug down about 6-8" between concrete. Leveled the bottom of the trench with sand and set concrete blocks all around to get a level perimeter. Front is about 18" higher than the back over 6' distance.
End of second day.
Day 3 (Feb 10, 2013): Framed up main structure in garage. Predrilled and precut everything. Moved the front and back walls separately and then started attaching the rafters. Attached plywood and tar paper. Then mocked up the tin roof. It isn't attached yet. Just held on with clamps for the moment. Since it is used roofing that was a find, it needs to come down to have my husband do his metal magic to fix the holes.
Mock up in the garage.
Plywood going on roof.
End of third day.
I am thinking at the rate we're going that we might actually be done by the time the eggs get here on the 20th. If not, then soon after.
What do you guys think?
Rachel